All but three of the doors have been installed, the frames "trued," and doors cut to allow for hardwood flooring to be installed. The window and door jam nail holes, along with stair skirting, have been filled and touch sanded.

Dave Fahey came over and adjusted the windows, replace one, and delivered some glass panes for inside the house.

The outside cement work is coming along, with the back framed out for a pour, and the front being pieced together for the stairs.

About a third of the cabinets have been installed. They are really nice oak pieces. The first one is one side of the family room.



This is the downstairs basement bathroom. There are four drawers instead on 3 on each side. I think this has to be changed.



A picture of the "remodel" house on the corner. Pretty cool - cement has been applied to the outside, I wonder what color it will be?



Master bath hanging cabinets





Laundry room uninstalled cabinet



Not sure what this one is, or where it goes.



Mini bar cabinet